Objectif
Ajouter une entrée à la section Productivité du rapport journalier à l'aide de l'application Procore sur un appareil mobile Android.
Contexte
The Productivity section allows you to track how much material arrives on site and how much is installed. Any "Approved" subcontracts or purchase orders with the Unit/Quantity accounting method will appear here so you can track the installation against the line items in the contract.
Éléments à prendre en compte
- Required User Permissions:
-
- To create entries:
- 'Standard' or 'Admin' level permissions on the project's Daily Log tool.
Note: Users must be able to view the relevant contract in order to add it to the Productivity entry. See View Commitments.
- To create pending entries as a collaborator:
- Additional Information:
- In order to complete a Productivity entry, you must ensure the following about the commitment:
- Limitations:
Procédure
- Ouvrez l'application Procore sur un appareil mobile Android.
- Accédez à l'outil Rapport journalier du projet.
- Appuyez sur la date pour sélectionner le jour calendaire auquel vous souhaitez créer une nouvelle entrée.
- Appuyez pour
créer une nouvelle entrée.
- Appuyez sur Productivité.
- Appuyez sur les champs suivants pour saisir les informations pertinentes :
- Contrat : sélectionnez le bon de commande ou l'engagement.
- Poste : sélectionnez le poste.
- Quantité livrée : saisissez le montant.
- Quantité mise en place : saisissez le montant.
- Appuyez sur Enregistrer.
Tip
If required fields are empty, click Fix Errors to go to the first empty field. Click Next Field or Previous Field to view other empty required fields.
After the required fields have been entered, you will be able to create or save the form.