Passer au contenu principal
Procore

Créer un ordre de changement au contrat principal

Objectif

Créer un ordre de changement au contrat principal dans l'outil Contrats principaux au niveau projet. 

Contexte

Suivez les étapes ci-dessous lorsque vous devez créer un ordre de changement au contrat principal.

Éléments à prendre en compte

Conditions préalables

Procédure

  1. Accédez à l'outil Contrats principaux du projet.
  2. Recherchez le contrat principal avec lequel travailler. Cliquez ensuite sur son lien Numéro.
  3. Cliquez sur Créer un OC de contrat principal.
    create-prime-contract-change-order.png
  4. Remplissez les champs suivants :
    • Sign with DocuSign®
      If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.

       Tip
      How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign® envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.
    • #
      Accept the default number, enter a new number, or create a custom numbering scheme for this change order and future ones. 

       Notes
      • Procore automatically assigns the item a new number in sequential order. For example; 001, 002, 003, and so on.
      • To use a custom numbering scheme, enter any set of alphanumeric characters. Procore automatically assigns new numbers in sequential order using your custom scheme. 
    • Date Created
      Shows the date and time the change order was created in Procore. You cannot change this date.

    • Revision
      If you revise a change order later, you can enter the revision number here.

    • Created By
      Procore automatically populates this field with the name of the user who created the change order. 

    • Title
      Enter a descriptive name here. 

    • Status
      Select the current status of the change order. Procore automatically places the change order in the 'Draft' status. To learn more, see What are the default statuses for change orders in Procore?

       
    • Private
      Mark this checkbox if you want the item to be private. This means it is only visible to users with 'Admin' level permissions on the contract (or funding). 

    • Due Date
      Select a due date to indicate the date by which the 'Designated Reviewer' must approve or reject the change order. 

    • Invoiced Date
      Select the date when the change order was invoiced. 

    • Designated Reviewer

      Select the Procore user at your organization who is responsible for approving or rejecting the change order. To appear as a selection in this list, the designated reviewer's Procore user account must be added to the Project Directory and have 'Standard' level permissions or higher to the contract or funding tool. See Add a User Account to the Project Directory

       Tip

      Are you the 'Designated Reviewer' on a change order? To learn how to submit an approve or reject response, see Approve or Reject a Change Order.

    • Paid Date
      Select the date that payment was received for the change order.

    • Description
      Enter a more detailed description of the change order. 

    • Schedule Impact
      If this change order is expected to impact the construction project's schedule, enter the estimated number of additional days this would add to the schedule. 

    • Revised Substantial Completion Date
      If the change order modifies the substantial completion date for the contract, select that date from the calendar control. 

       Note
      If the substantial completion date is enabled on the 'Configure Settings' page of the tool, Procore updates the change order's 'Revised Substantial Completion Date' field after the change order is placed into the Approved status. 
    • Executed
      Mark this checkbox after the change order is fully executed.

    • Selon les paramètres du niveau d'ordre de changement de l'outil Contrat principal, une (1) de ces cases de liste apparaîtra :
  5. Choisissez une (1) de ces options :
    • Pour créer l'ordre de changement, cliquez sur Créer.
      OU
    • Pour créer l'ordre de changement et envoyer des notifications par e-mail, cliquez sur Créer et envoyer par e-mail
      OU
    • Si vous utilisez l'intégration Procore + DocuSign® pour recueillir des signatures, cliquez sur  Terminer avec DocuSign. Pour en savoir plus, consultez DocuSign®.

 

If you would like to learn more about Procore's prime contract software and how it can help your business, please visit our construction contract management software product page icon-external-link.png.